Drinking water supply for Jamune: work has been completed
In January 2014 the water supply network´s project of Jamune and its scholastic centre was presented by the NGO Pro Nepal to the Autonomous Province of Bolzano; we received a financial support of 60% commission on the estimated amount.
Works and projects have been planned and we were about to finance a leftover 40% of the amount.
Unfortunately, due to the two earthquakes in 2015, we were forced to interrupt the planned project, because other needs took priority over it.
Despite the distance, our local partner SEO (society for each other) agreed to manage the project and the works, which began in autumn 2016 and lasted until December.
The final balance sheet and all the other papers were delivered to the Province of Bolzano just in time in order to get the payment.
During the earthquakes most of the buildings fell down, therefore the scheduled latrines haven´t been built and the final cost of the labour was 37.000 euro instead of 47.200 euro. In March 2017 Jamune was visited by a member of Pro Nepal and the President of SEO to make an inspection in order to verify the outcome. Two water tanks and the public water taps were checked. Because of the interrupted water inflow, the two water tanks were empty, therefore technicians solved the problem in a short time.
We worked hard on this project and put great care into it, but we´re glad that the village and the scholastic centre, which hosts almost 300 schoolchildren, can finally get running water.
All efforts have been made, therefore the fundamental right to water has been shielded with our strength, facing difficulties and obstacles, attaching importance to its meaning.