Majuwa drinking water system – Nepal

Project update March 2025

In September 2024, partial funding for the Majuwa drinking water project was approved (see our previous report).

In the meantime, a drinking water committee has been formed that has primarily worked to raise awareness among the local population for this important project and has also taken care of the awarding of the work. After an initial call for tenders, a company was identified to carry out the work. Unfortunately, formal problems arose, so the contract now had to be negotiated with another company.   The completion of the work will likely be delayed by a few months due to these problems.

However, a few days ago, our partner association SEO took part in the ceremonial laying of the foundation stone for the water reservoir construction.

Our partner association will continue to support and accompany the local population, the technicians and the drinking water committee throughout the entire project implementation.